Spring 2019 Construction Update

Posted:

None

With a team of over 80 workers on site we have seen much progress at Cromwell Place this year. The foundations for the Pavilion Gallery were laid and we have commenced the digging and construction of our 2,000 ft2 Art Storage and Plant Room. 
 

Meanwhile, in 1-4 Cromwell Place the Period Galleries are taking shape with over 90% of the Gallery floors re-laid with wifi cabling and electrics beneath. Plastering and restoration of Gallery walls continues across site. 
 

Preparations for the first floor link bridge between 4 and 5 Cromwell Place are well underway, with the structure to be fitted later this year. We are delighted to announce the completed restoration of roof tiling on buildings 1-4 Cromwell Place.
 

Written by: Cromwell Place